DETAILS OF CONTRACT/PURCHASES CONCLUDED
FOR TENDER NO : GEM BID NO. - GEM/2026/B/ 7867472 DATED: 18.08.2026 जीईएम बीड नं.- जीईएम/2026/बी/ 7867472 दिनांक: 18.08.2026
Unit Name : CURRENCY NOTE PRESS, NASHIK
Name of Contractor : M/S. GB CONTROLS AND SERVICES, NASHIK, MAHARASHTRA.
Value of Contract : 3,92,05,603
Item/Nature of work : प्रॉक्यूरमेंट ऑफ सप्लाइ, इन्स्टालेशन, टेस्टिंग अँड कमिशनिंग ऑफ एलटी पॅनल इन सब-स्टेशन 1,3 अँड गॅन्ग्वे ऑफ सीएनपी -1 /PROCUREMENT OF SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT ELECTRICAL PANEL IN SUB-STATION 1,3 AND GANGWAY OF CNP-1
Mode of Tender Enquiry : GEM
Date of Publication of NIT : 08/18/2026
Type of Bidding : 2 bid
Last Date of Receipt : 09/30/2026
Nos. of Tenders Recd.: 17
Nos. of Parties Qualified after technical evalution : 03
Nos. of Parties DisQualified after technical evalution : 14
Names of Parties Qualified after technical evalution : 1. M/S. GB CONTROLS AND SERVICES, NASHIK
2. M/S. SPECTRA ENGINEERING SYSTEM, NASHIK
3. M/S. VIDYUT CONTROLS AND AUTOMATION PVT. LTD., PUNE
Names of Parties DisQualified after technical evalution : 1. M/S. C AND D ELECTRICAL SOLUTIONS PRIVATE LIMITED, NASHIK
2. M/S. CHHABI ELECTRICALS PRIVATE LIMITED, JALGAON.
3. M/S. DQBYDT PRIVATE LIMITED, DELHI.
4. M/S. EXPERT ENGINEERING, NEW DELHI.
5. M/S. GEETU ELECTRICAL SYSTEMS PRIVATE LIMITED, UP
6. M/S. HAZZALE BLUE TRADING PRIVATE LIMITED, NEW DELHI.
7. M/S. LAXMI ELETRICAL, NASHIK.
8. M/S. BHOOMI CONTROLS, KANPUR.
9. M/S. RYB CONTROL SYSTEM, UP.
10. M/S. OM POWER SYSTEM, PANVEL.
11. M/S. OMKAR SWITCHGEARS, THANE.
12. M/S. POWER AUTOMATION AND CONTROL, MUMBAI.
13. M/S. RISH CONTROL ENGINEERS PRIVATE LIMITED, NEW DELHI.
14. M/S. SHIVALIC POWER CONTROL LIMITED, HARYANA.
Awarded to Lowest : Yes
Scheduled Date of completion of supplies :
Contract No : जीईएम कॉन्ट्रॅक्ट नं. जीईएम-511687754513249 दिनांक: 27.11.2026 GEM CONTRACT NO. GEM-511687754513249 DATED: 27.11.2026
Contract Date : 11/27/2026
Actual Date of Start of Work :
Actual Date of Completion :
Award Date : 11/27/2026
Award Upload Date : 11/27/2026
Reasons for delay if any :